What drawings do you need to build a house in India?

Approval drawings, construction drawings, structural and services drawings: what each one is for, and what goes wrong when one is missing.

Written by
The MIYAAR studio
Published
Last reviewed
Reading time
7 minutes
A stack of large-format construction drawings fanned across a concrete table

A house in India typically needs two different sets of drawings: approval (sanction) drawings for the local authority, and construction drawings for the builder. The construction set includes architectural plans, sections and elevations; structural drawings with reinforcement details; electrical and plumbing layouts; and schedules for doors, windows and finishes. Approval drawings alone are not enough to build from.

Most people building a home for the first time hear the word 'plan' and imagine one drawing. In practice a house is described by a set of drawings, each written for a different reader: the authority, the mason, the bar-bender, the electrician, the plumber and the person pricing the work. When one of those readers has no drawing, they make the decision themselves on site.

1. Approval (sanction) drawings

These are submitted to the local planning authority to show that the building complies with the rules for that plot: setbacks, height, built-up area, parking and similar. Their format and content are set by the authority, and requirements vary from state to state and city to city.

In Karnataka, some smaller residential plots in Bengaluru may be eligible for simplified self-certified approval schemes such as Nambike Nakshe. Eligibility depends on the plot and current rules, so it should be confirmed with the authority or a local professional before relying on it.

2. Architectural construction drawings

This is the set the builder works from. A complete one is dimensioned, coordinated and issued as Good for Construction (GFC). It usually includes:

  • Site plan with levels, setbacks and services connections
  • Dimensioned floor plans for every level, including the roof
  • Sections showing heights, slab levels and staircases
  • Elevations for every side
  • Door, window and finish schedules
  • Detail drawings for staircases, kitchens, bathrooms and junctions
  • Flooring layouts and levels

3. Structural drawings

Prepared by a qualified structural engineer from the architectural design and soil information. They cover foundations, columns, beams and slabs, with reinforcement schedules, so that the bar-bender and the concrete gang work from a drawing rather than from habit.

4. Services (MEP) drawings

  • Electrical: point layouts, lighting, switching, circuits and load provisions
  • Plumbing: water supply, drainage, sanitary layouts and slopes
  • Rainwater, sump and tank coordination
  • Air-conditioning and fire provisions where the scale requires them

The most expensive problems on a house site are usually clashes: a beam where a drain must pass, a duct with nowhere to go, a switch behind a wardrobe. Coordinating the services drawings with the architecture and structure on paper is far cheaper than cutting concrete later.

5. The bill of quantities (BOQ)

Not strictly a drawing, but the document that turns drawings into prices. A BOQ lists every item of work with quantities and a specification, so that different contractors quote the same scope and their numbers can actually be compared.

DocumentWritten forWhat goes wrong without it
Approval drawingsThe authorityNo legal permission to build
Architectural GFC setThe builderDimensions and details decided on site
Structural drawingsEngineer, bar-bender, siteReinforcement by habit, not design
MEP drawingsElectrician, plumberClashes cut into finished work
BOQ and specificationWhoever prices itQuotes that cannot be compared

What to ask before you start

  1. 01Which of these drawings is included in the fee, and which are extra?
  2. 02Who prepares and signs the structural drawings?
  3. 03Will the services drawings be coordinated with the structure?
  4. 04Will I own the drawings, and can I build them with any contractor?
  5. 05Who handles the approval submission for my plot and authority?

This guide is general information, not professional advice for a specific site. Requirements differ by state, authority and plot; confirm them with a qualified local professional before you rely on them.

Questions this raises

Are approval drawings enough to build a house?

No. Approval (sanction) drawings show the authority that the building complies with planning rules. They do not contain the dimensions, details, reinforcement or services a builder needs. Building from them alone leaves those decisions to be improvised on site.

What does GFC mean in construction drawings?

GFC stands for Good for Construction. It marks a drawing as checked, coordinated and issued for building from, as opposed to a concept or approval drawing.

Who should prepare the structural drawings for a house?

An appropriately qualified structural engineer, working from the architectural drawings and soil information for the actual site.

Related practice

Design

Authored design and a complete construction-ready set.

Explore Design

Bring us a question
worth answering.

Speak with MIYAAR

Discuss your project

Tell us a little. We will call you back.

1 · About you
2 · Type of project
3 · Your requirement

We use these details only to reply to this enquiry. Privacy · Prefer the detailed form?